Bitcoin hash rate falls 8% year over year despite a weekly rebound

Bitcoin’s hash rate, the computing power miners devote to the network, was 8% lower than a year earlier, Glassnode reported on Nov. 24, 2026. It was the first year-over-year decline since China’s 2021 mining ban. Glassnode attributed the drop to weaker Bitcoin prices as miners switched off machines with BTC trading near $60,000.

The shorter-term figures moved in the opposite direction. In its Nov. 23 weekly report, Luxor’s Hashrate Index said the seven-day average hash rate had risen 7.8% to 1,033 exahashes per second (EH/s), above the 30-day average of 1,019 EH/s.

Mining revenue held steady in bitcoin but fell in dollars

Glassnode said hashprice, the daily revenue a miner can expect from a given amount of computing power, had reached a record low. Luxor put dollar hashprice at $29.36 per petahash per second per day, down from $30.27 a week earlier. Measured in bitcoin, it was nearly unchanged at 0.000469 BTC. Miners could thus earn roughly the same amount of bitcoin from their machines but have fewer dollars available to pay electricity bills. Transaction fees averaged 0.0201 BTC per block, down from 0.0229 BTC the previous week.

Bitcoin’s mining difficulty fell 9.1% on Nov. 14. Luxor estimated on Nov. 23 that the next adjustment, expected around Nov. 26, would raise difficulty by 9.5%. That was a forecast, not a completed adjustment: miners had produced roughly three-quarters of the period’s 2,016 blocks, and the timing of the remaining blocks could still change the result.

If difficulty rose by 9.5%, a machine running at the same speed would earn about 8.7% less bitcoin per day, assuming unchanged uptime and average rewards per block.

What Riot and MARA count as mining costs

Riot Platforms reported an average cost of $39,265 per bitcoin mined in the September quarter, after power curtailment credits but before depreciation of its mining machines. Those credits totaled $24.7 million, or $15,067 per bitcoin produced. Including depreciation brought Riot’s cost to $78,805 per coin, above the $70,855 average value it reported for the bitcoin it mined.

MARA Holdings reported a narrower figure: purchased electricity cost $39,674 per bitcoin at company-owned sites, with maintenance and third-party hosting expenses reported separately. Its quarterly cost per petahash per day averaged $30.80. That was $1.44 above Luxor’s Nov. 23 hashprice, though the comparison is between a company’s costs averaged over a quarter and network revenue on a single day.

Bitcoin sales funded loan repayments and data centers

MARA raised about $1.1 billion by selling 13,597 BTC after Sept. 30. It used $750 million to repay bitcoin-backed term loans, releasing 17,477 BTC pledged as collateral. MARA said it may use further sales to fund artificial intelligence infrastructure and meet repayment obligations if convertible noteholders exercise their rights in 2027.

Riot sold 20,264 BTC in the first nine months of 2026, more than four times the 4,697 BTC it mined. It said the sales raised about $1.5 billion, primarily for data center development. Riot also repaid its $200 million Coinbase credit facility and reported a 15-year lease with an unnamed AI company for 910 megawatts of computing capacity at its Corsicana campus in Texas.

HIVE Digital Technologies sold about 93% of the bitcoin it mined in the September quarter but still added 79 BTC to its treasury, bringing its holdings to 269 BTC. It recorded $8.8 million in quarterly high-performance computing revenue.

Bitdeer said in a Nov. 21 update that it sold its entire weekly output of 281.1 BTC and ended the week of Nov. 20 with no company-owned bitcoin, excluding customer deposits. Its September-quarter filing showed $221.5 million in proceeds from digital asset sales, primarily mined bitcoin, and $1.95 billion in borrowings as of Sept. 30.

Of Bitdeer’s $478 million in quarterly capital spending, about $110 million went toward producing and deploying mining machines, including freight and tariffs. The company attributed most of the remaining $368 million to data center construction and purchases of graphics processors.